Tel: +44 (0)1788 555 020

 

 

Causes of Pavement Deterioration

Leading to Reflective Cracking
 
Excessive wheel loading way beyond original design.    
 
Ingress of water, de-icing salts and debris at joints and fault cracks.    
 
Subsidence of sub-grade/sub-base.    
 
Warping and over stressing of the rigid pavement.    
 
Failure in the rigid pavement due to the inability of construction joints to accommodate thermal expansion/construction movements.    
 
Lack of load transfer at dowel tie bars.    
 
Rocking road slabs and temporary reinstatements.    
 
Failure of joint sealant/cracks in sealant.    
 
Corrosion or spalling of concrete pavement.    
 
Voiding of sub-base/sub-grade.    
 
Where utility companies maintenance/upgrading has caused weakness and failure.    
   
Summary
   
   
Any one or a combination of these factors can cause reflective cracking in overlays. Cracking and Seating can remedy all of these failure mechanisms to ensure that even a minimum overlay will not fail due to reflective cracking.
   
         
   
Why Cracking & Seating must be considered as an option for remedial and maintenance
   
   
A Dtp directive states that a bituminous overlay in the region of 150mm/180mm is usually adequate to prevent/control reflective cracking as long as all existing defects in the grid pavement have been repaired before overlaying, or failure or reflective cracking can occur.
It is probably unlikely in most cases to economically carry out these repairs, and apply an overlay of this depth, even an overlay, half the recommended thickness may be not possible where existing levels, thresholds or costs prohibit. Cracking and Seating allows for the treatment of all existing defects and the application of an overlay to meet existing levels or new design.
   
   
What are the real maintenance options?
   
  1. Overlay with 150/180mm overlay.    
  2. Full depth reconstruction of pavement with flexible construction.    
  3. Do nothing and overlay.    
  4. Crack and Seat and resurface with a reduced depth of overlay.    
   
Obviously it is not long term cost effective or permanent to do nothing, as all mechanisms that have caused the rigid pavement to fail will continue to operate throughout the concrete road base. Cracking and Seating is easily the best option from the above as it is cost effective, fast, reliable and practical.
   
   
Consider these four prime factors:
     
  1. The consequences of not carrying out repairs to the pavement.      
  2. The ability of just overlaying to control reflective cracking.      
  3. Cost effectiveness.      
  4. Long term durability.      
   
Footnote:
     
   
After considering all these options, factors and recommendations Cracking and Seating is simply the most cost effective, lasting and easiest method of maintenance to concrete road based carriageways.
     
   
   
         
© 2005 Highway Systems Limited
Designed by CCUK